Injaz Building – Dubai
Project Overview
CDE Engineering Services was commissioned by Water Seal LLC to carry out a preliminary condition assessment of post-tensioned (PT) tendons at selected locations in the ground floor and basement slab of the Injaz Building in Dubai.
The assessment focused on evaluating the condition of PT tendons and identifying potential risks related to deterioration.
Client
Technical Expert Consultant & Project Managers, Sharjah, UAE
Location
Dubai, UAE
Client Challenge
Concrete delamination and spalling were observed in slab soffits around PT tendon zones in the ground floor and basement levels. The client required an assessment to understand the cause of distress and to evaluate the likelihood of corrosion in PT tendons.
Scope of Work
Our Approach
CDE carried out a focused preliminary investigation involving site inspection and assessment of visible distress. Observations were used to evaluate the condition of PT tendons and to identify areas requiring further detailed investigation.
Key Findings
Solutions & Recommendations
Outcome
The assessment established the condition of slab areas and highlighted the need for further detailed investigation of PT tendons. This supports informed decision-making regarding repair and investigation planning.